Progress of 24 Montgomery Kogarah

August 2020

Dear valued clients,

We are pleased to update you on the construction progress, of 24 Montgomery Street.

  • We have completed 38% of the works
  • Formwork to level 3 is now complete
  • All structural walls below are complete
  • Formwork stripping of the basement is nearing completion

We look forward to updating you again next quarter with the construction progress.